Baltimore Regional
Partnership
April 16, 1999
Mr. Richard Spencer
US Army Corps of Engineers
Attn: CENAB-OP-RX
PO Box 1715
Baltimore, MD 21203-1715
Re: Comments regarding US 1 Bel Air Bypass
from MD 147 to North of MD 924 project
Dear Mr. Spencer:
Please accept the following written
comments on the proposed project for the US 1 Bel Air Bypass as described
in the "Location/Design Public Hearing" brochure and the
"Environmental Assessment, Project No. HA888B12". We thank you
for extending the comment period.
i. Overview
As stated in our earlier comments on the
Bel Air Bypass project as proposed in the Baltimore Regional
Transportation Plan, we recommend that this proposed project be rejected.
We oppose all build alternatives because they: (1) will unnecessarily harm
valuable aquatic resources, (2) do not address the community’s
transportation needs, (3) violate Maryland’s Smart Growth laws and
policies, and (4) fail to meet minimum justification under federal
regulations. The current two-lane Bypass has excellent access control and
does a good job of diverting through traffic from the town of Bel Air.
Widening the Bypass to four lanes would simply make it a purveyor of new
sprawl development to the northern and eastern portions of Harford County.
The Bypass, coupled with other major road projects, such as the Hickory
Bypass, appears to serve the purpose of avoiding established communities
in order to conduct more growth to rural areas outside the Bel Air
Priority Funding Area (PFA) and the County’s Development Envelope.
No attempt is made in the Environmental
Assessment (EA) to assess the direct, secondary and cumulative
environmental impacts of this project. The deleterious effects on valuable
wetlands, streams and other environmental resources resulting from all the
build alternatives are unacceptable because the transportation goals of
the project will not be met by the proposed action. Thus, the
environmental impacts are unnecessary and wholly avoidable. For the
reasons described below, we ask that the permit for proposed impacts to
wetlands, streams and other natural resources regulated by Section 404 of
the Clean Water Act be denied.
II. Environmental Impacts Assessment
The project proposes to further degrade
valuable wetlands adjacent to Winters Run and Route 1 that were once high
quality wetlands. Records of the federally-protected Bog Turtle occurring
in the area and potential Bog Turtle habitat identified by Maryland
Department of Natural Resources demonstrate the quality of these wetlands.
This wetlands system cannot afford further disturbance and destruction,
especially if habitat for federally-protected Bog Turtle exists.
Wetlands in the project area which are
adjacent to Winters Run were formerly part of a high value wetlands system
that has been degraded by the construction of Route 1 and County Park
development. Valuable wetlands habitat, however, still remains and should
be protected. The proposed project will have significant direct effects on
these wetlands through disturbance, filling, and increased runoff volume
affecting the hydrology of this groundwater–fed wetlands system. The EA
fails to consider the hydrological effects of the proposed action.
The Environmental Assessment (EA)
acknowledges that increased impervious surface cover, disturbance, and
destruction of wetlands and streams and streambeds are harmful to surface
water quality. The EA also acknowledges that the increased impervious
surface from the project will impede groundwater recharge. Despite the
availability of a number of broadly accepted methods for assessing the
direct water quality impacts of such actions, the EA makes no attempt to
estimate direct pollutant loadings that can be reasonably expected to be
generated from the project.
The EA states that it chose the Secondary
and Cumulative Effects Analysis (SCEA) boundary based on subwatershed
boundaries and has much natural resource information available at the
subwatershed level. Although the Maryland Office of Planning and Maryland
Department of Natural Resources have well developed Geographic Information
Systems to assist in specifically examining the cumulative environmental
effects of the proposed project on a subwatershed basis, the EA failed to
utilize these readily available information sources and analytical tools.
It is unacceptable that the EA would set boundaries based on subwatersheds,
acknowledge the availability of natural resource information to assist in
direct and cumulative effects analysis specifically aggregated at the
subwatershed level, and then not perform any kind of an analysis on the
project’s environmental effects.
In the case of the Winters Run
subwatershed, even more information is available regarding cumulative
effects of development on water quality as Maryland Office of Planning has
worked with the County to model different development scenarios and their
impact on water quality. At the very least, results from Office of
Planning’s "Watershed Planning System" analysis of Winter’s
Run subwatershed should be used to examine the direct, but especially
cumulative, effects of this project. Results from this analysis conducted
by the Office of Planning demonstrate that land use or "directed
growth" techniques yield the greatest benefit, and that stormwater
management techniques yield the least. Thus, actions that avoid increased
impervious surface coverage are much more desirable than stormwater
"Best Management Practices". The EA, however, glibly states that
"discharge of pollutants and the temperature increase of runoff can
be controlled through the use of stormwater management practices."
The EA fails to provide a serious analysis or use readily available
information regarding possible water quality effects of the build
alternatives. At the same time, the EA promotes an uncritical acceptance
of engineered stormwater management practices as a cure to any possible
project impacts on aquatic resources. We find this assessment unacceptable
and inadequate as a basis for assisting the public in making an informed
decision about the trade-offs of the proposed action.
The proposed project impacts from
construction, numerous stream crossings, placement of culverts, other
streambed alterations, and encroachment on 100 year floodplains are not
adequately assessed in the EA. The proposed action will have direct
temporary and long-term effects on water quality and aquatic resources.
None of these are addressed in the EA. While sediment and erosion control
measures for construction and stormwater management Best Management
Practices are important tools for mitigating the effects of damaging
actions on water quality, it is important to recognize their limitations,
especially when valuable resources are at risk. Many of these practices
are untested over the long-term and regularly fail for any number of
reasons, including: unknown design flaws, maintenance shortcomings,
vandalism, natural failure or negative influences, and gradual
deterioration.
Not only does the EA fail to provide
useful natural resources information and analysis in general or at the
subwatershed level, but the boundary for Secondary and Cumulative Effects
Areas boundary (SCEA) also fails to incorporate the most important area of
influence for analysis. The boundary for the SCEA fails to incorporate the
area that is most at risk of detrimental effects from this project –
rural lands to the north and east. This road project which seeks to
provide a more rapid link between urbanized and rural areas will clearly
accelerate and encourage new development outside PFAs. The SCEA boundary
must be extended to the north and east beyond the Hickory Bypass to
capture the ever broadening "commute-shed" created by perceived
or real reduced travel times. Higher speed travel on the road generates
perceived or real reduction in travel times causing rural areas remote to
major job centers to be more desirable for commuters. The secondary
development induced (in the broadened commute-shed) by this project will
generate a significant amount of increased impervious surfaces, new
sources of polluted suburban runoff (e.g. intensively managed and
compacted lawns), and new losses of natural resources such as wetlands,
forests, floodplain encroachment and impacted streams.
These secondary and cumulative effects
must be assessed as part of this project analysis and in combination with
the Hickory Bypass process. To neglect to assess the cumulative effects of
the Bel Air Bypass build alternatives along with the impacts from the
Hickory Bypass amounts to segmentation, which is illegal under the
National Environmental Policy Act.
III. Traffic Analysis
We believe the build alternatives to be
unnecessary and counter-productive, and thus the impacts to wetlands,
streams and other natural resources wholly avoidable, for the following
reasons:
Upgrading the Bypass would attract more
sprawl to Forest Hill, Hickory and other heretofore rural areas in north
Harford County.
Upgrading the Bypass does nothing to
improve capacity or reduce congestion at the key adjacent intersections
which connect Bel Air to the rest of the Baltimore urbanized area,
particularly the intersection of MD 24 and US 1 Business, and the
intersection of US 1, US 1 Business and MD 147.
Upgrading the Bypass ignores the more
relevant and important issue of making the town center of Bel Air more
livable and attractive. Solutions need to be identified and implemented
which will resolve the uneasy coexistence of traffic and activity in the
town center. The Bypass is not a viable traffic alternative for the vast
majority of the through trips which impact the Bel Air town center,
including traffic destined for Churchville and Aberdeen.
Detailed discussion of traffic operations
and the proposed build alternatives
The project does not appear to provide
more capacity at the locations where capacity is a major issue. Basically,
the Bypass connects four specific points:
The intersection of US 1 and MD 147 west
of Bel Air - This intersection operates on a three phase traffic signal.
MD 147 to the west and US 1 Business to the east each have separate
signal phases, while the bypass approach and the US 1 approach from the
south move in tandem. This is a very inefficient way to operate an
intersection and greatly reduces the overall capacity relative to a
conventional two phase signal, but it is necessary because of the heavy
left turn movements on MD 147 and US 1 Business. The Bypass project does
nothing to increase the capacity of this intersection.
MD 24 at US 1 (Business) at the Harford
Mall within Bel Air - This huge intersection also has very heavy
left-turn movements and operates from a complex multi-phase signal
controller. MD 24 to I-95 is now the primary connection from Bel Air to
Baltimore, rather than US 1. Moreover, this section of MD 24 is now the
major retail area of Harford County. Most likely due to the excellent
access control on the bypass, retail development has predominately
stayed in this area of central and southern Bel Air, rather than
migrating outward and northward to the sprawl area. The Bypass project
does nothing to increase the capacity of this or the surrounding
intersections and driveways.
MD 24 north of Bel Air toward Forest
Hill - MD 24 north of the Bypass is one of the latest "sprawl
frontiers" in Harford County. Just north of the Bypass, MD 24 is a
dualized roadway with two through lanes in each direction. Northward, as
development begins to be more scattered, it becomes a standard two lane
road. Both lanes of southbound MD 24 are permitted to access a two lane
ramp to the southbound Bypass, while a third ramp lane is dedicated to
the left turn from the northbound access point. All three ramp lanes
merge into a single dedicated lane on the Bypass. Traffic wishing to
continue on southbound MD 24 (see Number 2 above) must move over one
lane to the left. This ramp connection would be unchanged under all of
the alternatives.
US 1 at MD 23 toward Hickory northeast
of Bel Air - Hickory and the area beyond it to the north and east toward
Conowingo and Pennsylvania is also a burgeoning sprawl development area.
An improved connection from the north end of the Bypass to MD 23 and US
1 is being planned as a separate project in the State's Consolidated
Transportation Plan. However, the Bypass connection itself at this point
will still have only two lanes, with no apparent increase in the overall
through capacity.
In sum, there would essentially be no
capacity increase to any of the Bypass connections. What would increase is
the capacity of the Bypass itself, by virtue of an upgrade of its
intersection with MD 24 South. It takes up more land than the entire Bel
Air town center, and is over a mile long.
Since none of the Bypass connections would
have greater capacity as a result, the proposed intersection/interchange
improvements would translate directly into greater speed,
particularly for the left-turn from southbound US 1 / MD 24 to southbound
MD 24. Speed is the traffic parameter which is most acutely perceived by
the motoring public. This speed increase will therefore translate most
directly into acceleration of development outside PFAs and the Development
Envelope.
Perhaps there actually is a bottleneck
along the Bypass that prevents it from most efficiently serving the four
points listed above. If so, a large traffic circle might be an appropriate
solution, although there may be other solutions that are specific and
limited.
IV. Conclusion
We find the EA wholly inadequate for
assessing the direct, secondary and cumulative effects of the project on
valuable wetlands, streams and other natural resources. Furthermore, based
on our above traffic operations analysis, we find that all build
alternatives fail to address the transportation needs of the Bel Air area,
and only serve to encourage growth outside PFAs. Thus the project’s
direct, indirect and cumulative impacts on valuable aquatic resources are
completely unnecessary, eminently avoidable, and would result in the
violation of State Smart Growth laws. For these reasons, we ask that you
deny a permit under Section 404 Authorization for this proposal.
We thank you for the opportunity to
comment on this project.
Sincerely,
Alfred W. Barry, III
Chairman, Committee on the Region
Citizens Planning and Housing Association
218 W. Saratoga Street
Baltimore, MD 21201
Dru Schmidt-Perkins
Executive Director
1000 Friends of Maryland
11˝ W. Chase Street
Baltimore, MD 21201
Michael Replogle
Director, Federal Transportation
Environmental Defense Fund
1875 Connecticut Ave. NW
Washington, DC 20009
Lee Epstein
Director, Lands Program
Chesapeake Bay Foundation
162 Prince George Street
Annapolis, MD 21401
Andrew D. Sawyers
Director, Environment Program
Baltimore Urban League
512 Orchard Street
Baltimore, MD 21201